Schedule and lead time

How long the kitchen is out, and the one date that decides it

Two reasons a kitchen runs long are that the cabinets were ordered too late, or that nobody counted the wait between the countertop template and the countertop arriving. Both are waiting rather than working, and waiting may not appear on a contractor's day count.

The dependency chain, and the date it works back to

Cabinets
weeks
weeks
days
Work phases
days
days
days
days
days
days
days
Inspections and household
days
USD

Latest date the cabinets can be ordered

0.4 weeks ago

The order is already behind the schedule below. The day count on this page adds no delay for that, so the real finish date moves out by at least that much.

Days in the chain 45 work and wait days added; weekends not counted
Days with work happening 26
Days waiting 19
Days without a kitchen 43
Extra food spending $813 over the out-of-service period
Counter fabrication wait 11 days sequential, after the cabinets are set

Of 45 days in this chain (work days and wait days added; weekends not counted), 26 have someone working in your kitchen and 19 are waits. The total assumes the cabinets arrive on time; it adds no delay for a late order. If the order date shown above is in the past, the real finish date moves out by at least that much.

  • The cabinet order needed to be placed 0.4 weeks ago to keep the site moving. The day count on this page adds no delay for a late order, so the real finish date moves out by at least that much.

The chain, phase by phase

PhaseDaysKindWhat is actually happening
Demolition and haul-out3workThe kitchen becomes unusable on day one of this phase, not on the day the cabinets come out.
Rough plumbing, electrical and framing5workEverything that has to happen before a wall can be closed. The scope of this phase is decided by how many services move.
Inspection holds8inspection2 inspections at 4 days of waiting each. Nothing can be covered until each one passes, and a failed inspection adds another wait.
Drywall, prime and paint6workMud has to dry between coats, which is why this phase resists being compressed by adding people.
Flooring3workThis tool schedules flooring before the cabinets, so the cabinets sit on the finished floor and a future appliance can slide in and out.
Cabinet set4workCannot start before the cabinets arrive. This is the point where a late order stops the work.
Countertop template to install11waitThe counter cannot be templated until the cabinets are set and level, and cannot be fabricated until it is templated. This wait is sequential with everything before it and is easy to leave off a schedule.
Plumbing and electrical trim-out3workThe sink cannot be connected until the counter is in, so the plumber returns after the fabricator leaves.
Punch list2workDoors adjusted, filler scribed, touch-up paint, the drawer that binds. Short, and easy to forget to schedule.

The Kind column is the one that matters. Work can sometimes be compressed by adding people; the two waits in this chain — inspections and countertop fabrication — are sequential with everything around them in this tool.

Lead time by grade, and why it decides everything else

GradeWhat it meansBand this tool assumes (ours, not a published figure)What the lead time is doing
Stock, carried in the warehouseBoxes already sitting in a warehouseDays to two weeksLittle: this grade can take the cabinet order off the critical path.
Stock line, special orderStandard sizes, built to a batch scheduleThree to six weeksWaiting for the factory to reach your batch.
Semi-customStandard boxes, modified sizes and finishesSix to twelve weeksA finish queue and a modification queue.
Full custom, built for this roomBuilt for this room by a shopTen to twenty-four weeksA shop's order book ahead of yours, plus the finish.

These are our own rough bands, not a published survey; the tool uses them only to flag a quoted lead time that looks unusually short or long. Your supplier's written lead time is the number that counts. If a supplier quotes a lead well under the band, that is worth a written confirmation, because the schedule above is standing on it. If they quote well over, ask whether it is the shop queue or the finish, since a finish change can sometimes recover weeks and a queue position cannot.

The cost that is not on any bid

This kitchen is out of service for 43 days. That is not a construction cost and no contractor will put it on a quote. At the $42 a day entered above, that is $1,806; because a temporary kitchen is ticked, this tool counts 45% of it — our own assumption about how much a temporary kitchen saves, not a measured figure — which comes to $813.

The disruption figure uses a daily amount of ours, and it is a control above so you can replace it: Assumed extra food spending per household per day while the kitchen is out of service, above what the household would have spent cooking at home. It is a placeholder for your own number, and yours is the one that matters.