Schedule and lead time

How long the kitchen is out, and the one date that decides it

Almost every kitchen that runs long runs long for one of two reasons: the cabinets were ordered too late, or nobody counted the wait between the countertop template and the countertop arriving. Both are waiting rather than working, and waiting does not appear on a contractor's day count.

The dependency chain, and the date it works back to

Cabinets
weeks
weeks
days
Work phases
days
days
days
days
days
days
days
Inspections and household
days
USD

Latest date the cabinets can be ordered

0.4 weeks ago

The order is already behind the schedule below. Every further week is a week the crew stands still after the floor goes down.

Calendar days 45
Days with work happening 26
Days waiting 19
Days without a kitchen 43
Extra food spending $813 over the out-of-service period
Counter fabrication wait 11 days sequential, after the cabinets are set

Of 45 calendar days, 26 have someone working in your kitchen and 19 do not. The waiting is not slack in the schedule — it is the schedule. Compressing the 26 working days by hiring a bigger crew changes the finish date by very little; moving the cabinet order earlier changes it a lot.

  • The cabinet order needed to be placed 0.4 weeks ago to keep the site moving. Every week from here is a week the crew stands still after the floor goes down, and that is dead time you are usually paying for.

The chain, phase by phase

PhaseDaysKindWhat is actually happening
Demolition and haul-out3workThe kitchen becomes unusable on day one of this phase, not on the day the cabinets come out.
Rough plumbing, electrical and framing5workEverything that has to happen before a wall can be closed. The scope of this phase is decided by how many services move.
Inspection holds8inspection2 inspections at 4 days of waiting each. Nothing can be covered until each one passes, and a failed inspection restarts its own wait.
Drywall, prime and paint6workMud has to dry between coats, which is why this phase resists being compressed by adding people.
Flooring3workLaid before the cabinets in most builds, so the cabinets sit on the finished floor and a future appliance can slide in and out.
Cabinet set4workCannot start before the cabinets arrive. This is the point where a late order stops the entire site.
Countertop template to install11waitThe counter cannot be templated until the cabinets are set and level, and cannot be fabricated until it is templated. This wait is sequential with everything before it and is the most commonly omitted item on a schedule.
Plumbing and electrical trim-out3workThe sink cannot be connected until the counter is in, so the plumber returns after the fabricator leaves.
Punch list2workDoors adjusted, filler scribed, touch-up paint, the drawer that binds. Short, and almost never scheduled.

The middle column is the one that matters. Work can sometimes be compressed by adding people. Waiting cannot be compressed at all, and the two waits in this chain — inspections and countertop fabrication — are both sequential with everything around them.

Lead time by grade, and why it decides everything else

GradeWhat it meansTypical leadWhat the lead time is doing
Stock, carried in the warehouseBoxes already sitting in a warehouseDays to two weeksNothing. This grade takes the cabinet order off the critical path entirely.
Stock line, special orderStandard sizes, built to a batch scheduleThree to six weeksWaiting for the factory to reach your batch.
Semi-customStandard boxes, modified sizes and finishesSix to twelve weeksA finish queue and a modification queue, usually in series.
Full custom, built for this roomBuilt for this room by a shopTen to twenty-four weeksA shop's entire order book ahead of yours, plus the finish.

These are the bands the tool checks your quoted lead time against. If a supplier quotes a lead well under the band for their grade, that is worth a written confirmation, because the entire schedule above is standing on it. If they quote well over, ask whether it is the shop queue or the finish, since a finish change can sometimes recover weeks and a queue position cannot.

The cost that is not on any bid

This kitchen is out of service for 43 days. That is not a construction cost and no contractor will put it on a quote, but it is money leaving the household every single one of those days, and on these numbers it comes to $813.

The disruption figure uses a daily amount that is ours and is almost certainly wrong for your household. It is exposed as a control above for exactly that reason: Assumed extra food spending per household per day while the kitchen is out of service, above what the household would have spent cooking at home. It is a placeholder for your own number, and yours is the one that matters.