Two worked examples, run through the calculator engine itself

Every derived number on this page — the cabinet linear feet, the box count, the trade hours, the tier, the subtotal — comes from the same whole-project formula the homepage calculator uses, run against two different, complete input sets. No derived quantity below is typed in as a literal. The unit prices that feed those quantities ARE typed in, on purpose: they are illustrative example prices, not sourced market data, chosen to be different between the two examples the same way two real bids would differ — see the callout below.

Example A — a same-footprint replacement in a 1990s suburban kitchen

An L-shaped kitchen, roughly 12 by 10 feet, with two runs of cabinets that stay exactly where they are. One new circuit, no fixture moves, no walls opening. This is the least disruptive real scope this site models, and the tier below falls out of that automatically.

Derived subtotal, before contingency

$17,473

Scope tier: Same-footprint replacement.

Range from published wage spread $16,486 to $18,883

Cabinets and counters are replaced where they stand. Nothing moves, no inspection sits on the critical path, and the finish level is genuinely the main variable.

Cabinet linear feet 18.0 derived from the room
Cabinet boxes 7
Trade hours 74.1 across the trades this scope employs
Labour share 29% of the derived subtotal
Cost per cabinet foot $971
Materials subtotal $12,202
Material lineQuantityUnit priceLine total
Cabinetry18 linear ft (7 boxes)$260$4,680
Cabinet hardware7 boxes$14$98
Countertops23.4 sq ft, 11 ft of exposed edge$55$1,287
Appliance packageas specified$4,200$4,200
Sink, faucet and disposal1 set$550$550
Lighting fixturesas specified$320$320
Backsplash material24.8 sq ft$14$347
Flooring material120 sq ft$6$720
TradeHoursBilled at median wage (burdened)
Carpenters (SOC 47-2031)32.9$2,108
Tile and Stone Setters (SOC 47-2044)21.8$1,286
Electricians (SOC 47-2111)11.4$759
Plumbers, Pipefitters, and Steamfitters (SOC 47-2152)4.0$270
Painters, Construction and Maintenance (SOC 47-2141)4.0$211

That "billed" column is not the published median wage itself — it is hours times the published median wage times this site's own 2.2x wage-to-billed multiplier (an assumed figure, disclosed on the methodology page, not something BLS publishes).

The four pieces that add up to the subtotal aboveAmount
Materials subtotal (table above)$12,202
Direct labour, burdened (trade table above, summed)$4,634
General conditions (an assumed fraction of direct labour)$417
Permits (the illustrative example permit fee)$220
Total — matches the derived subtotal above$17,473

Not in this subtotal

  • Anything behind a wall that nobody has looked behind yet
  • Structural repair discovered during demolition
  • Asbestos or lead testing, abatement and clearance
  • Bringing unpermitted earlier work into compliance
  • Appliance delivery, installation and haul-away of the old units, unless your appliance quote says otherwise
  • Window, door and exterior repairs triggered by a new vent termination
  • Temporary kitchen setup and the cost of eating out
  • Sales tax, financing cost and any contractor deposit that is non-refundable

Example B — a gut-and-relocate in a 1930s bungalow, with an island added

A larger room with an island, custom cabinetry, two fixtures relocating and the walls opening to the studs to run six new circuits. Every trade this site models shows up here, and several of them show up twice — once in rough-in, once in trim-out.

Derived subtotal, before contingency

$54,691

Scope tier: Gut and relocate.

Range from published wage spread $52,226 to $58,205

Walls are opening and services are moving, so every trade rough-ins and returns to trim, with inspections between. This is the tier where the schedule, not the finish level, sets the cost.

Cabinet linear feet 37.7 derived from the room
Cabinet boxes 11
Trade hours 179.4 across the trades this scope employs
Labour share 23% of the derived subtotal
Cost per cabinet foot $1,451
Materials subtotal $41,398
Material lineQuantityUnit priceLine total
Cabinetry37.7 linear ft (11 boxes)$480$18,096
Cabinet hardware11 boxes$32$352
Countertops57.7 sq ft, 35.3 ft of exposed edge$92$5,308
Appliance packageas specified$11,800$11,800
Sink, faucet and disposal1 set$1,350$1,350
Lighting fixturesas specified$1,450$1,450
Backsplash material29 sq ft$26$754
Flooring material208 sq ft$11$2,288
TradeHoursBilled at median wage (burdened)
Carpenters (SOC 47-2031)73.3$4,693
Tile and Stone Setters (SOC 47-2044)36.1$2,129
Electricians (SOC 47-2111)29.7$1,987
Plumbers, Pipefitters, and Steamfitters (SOC 47-2152)19.0$1,282
Drywall and Ceiling Tile Installers (SOC 47-2081)15.8$985
Painters, Construction and Maintenance (SOC 47-2141)5.5$285

That "billed" column is not the published median wage itself — it is hours times the published median wage times this site's own 2.2x wage-to-billed multiplier (an assumed figure, disclosed on the methodology page, not something BLS publishes).

The four pieces that add up to the subtotal aboveAmount
Materials subtotal (table above)$41,398
Direct labour, burdened (trade table above, summed)$11,361
General conditions (an assumed fraction of direct labour)$1,022
Permits (the illustrative example permit fee)$910
Total — matches the derived subtotal above$54,691

Not in this subtotal

  • Anything behind a wall that nobody has looked behind yet
  • Structural repair discovered during demolition
  • Asbestos or lead testing, abatement and clearance
  • Bringing unpermitted earlier work into compliance
  • Appliance delivery, installation and haul-away of the old units, unless your appliance quote says otherwise
  • Window, door and exterior repairs triggered by a new vent termination
  • Temporary kitchen setup and the cost of eating out
  • Sales tax, financing cost and any contractor deposit that is non-refundable

What actually changed between the two, and why

Example AExample B
TierSame-footprint replacementGut and relocate
Subtotal (mid)$17,473$54,691
Labour share of subtotal29%23%
Trade hours74.1179.4
Cost per cabinet linear foot$971$1,451

The subtotal moved by more than a factor of three, but the labour SHARE of the subtotal actually fell in the bigger job, because Example B’s materials — custom cabinetry, a larger island, a bigger appliance package — grew faster than the trade hours did. That is the opposite of the intuition most people bring to "a bigger job means labour matters more," and it is exactly the kind of thing a formula shows that a rule of thumb hides.

Both examples price every trade hour from the same six national wage rows this site sources from the Bureau of Labor Statistics — the median carpenter wage behind both is $29.12/hr — so the labour side of both totals traces to the same source data, not a different assumption per example. The materials side does not hold the price constant on purpose: Example B pairs larger derived quantities with higher illustrative unit prices, the way a custom-grade, larger-island scope plausibly would, though neither set of prices is a sourced market figure. Read the subtotal gap as "a bigger job at a higher illustrative grade," not as a clean test of quantity with price held fixed — if you want that cleaner comparison, run both scopes through the whole-project calculator with the SAME unit prices entered for each.

Run your own numbers

The whole-project calculator starts from a third, different kitchen by default. Change the room, the runs, the scope switches and your own local unit prices, and the same formula that produced both examples above will produce yours.