Drain relocation
Can the sink actually move, and what happens to the budget if it cannot
Moving the sink can turn a predictable job into an open-ended one. Moving a sink is not moving a faucet. The waste line has to fall continuously all the way to where it meets the existing stack, and a floor only has so much depth to give it.
Can the drain physically get there
Derived feasibility
Not inside this floor
The drain needs 5.13 inches of vertical room and the floor offers 4.58. It is short by 0.54 inches, so this move cannot be made inside the existing floor at 0.25 inch per foot.
Trades this move brings in Plumber
- At this slope the furthest the trap can travel inside the floor is about 8.8 feet. Shortening the move to that distance avoids the alternatives below.
- With a crawlspace or open space below, the line can run below the joists; with a finished ceiling below it means a soffit or a ceiling repair. Sistered or engineered joists and a sewage ejector are the other options, and each is a larger job than the sink.
- The vent has to move with the fixture. Re-venting adds plumbing time, because the vent has to reach a stack or the roof and has its own routing rules.
- Running across the joists means boring each joist in the path; this tool assumes only one third of the joist depth is usable for that, which is our own simplification, not a code figure.
The arithmetic, in full
- Required fall. The trap moves 11 feet and the line must drop 0.25 inches for each foot it travels, so it needs 2.75 inches of vertical drop end to end.
- Depth the pipe occupies. Add the outside diameter of the pipe and its fittings, 2.375 inches, giving 5.13 inches of vertical space the floor has to contain.
- Depth the floor offers. Running across joists, this tool counts one third of the joist depth as usable (our own simplification, not a code figure). That gives 3.08 inches, plus 1.50 inches of build-up above the joists, for 4.58 inches.
- The margin. 4.58 minus 5.13 is -0.54 inches (worked from the unrounded depths). Positive means it fits. Negative means the move, at this slope, does not happen inside this floor.
- The useful inversion. Rearranged, the furthest the trap can travel and still fit is 8.8 feet. That number is worth more than the verdict, because it tells you where to put the sink instead.
What actually costs money when the answer is no
Opening a ceiling below
If the room underneath is finished, the drain route runs through somebody's living room ceiling. The plumbing itself might be a day. The ceiling repair, the texture match, the paint and the fact that the room has to be emptied are all separate line items in a room that was never part of the remodel.
Cutting a slab
On grade there is no cavity at all, so the line goes below the concrete. That means saw-cutting a trench the length of the run, breaking out and removing the spoil, laying and inspecting the new line while the trench is open, then filling, patching and levelling before any floor goes down. If your inspector needs to see the trench open, that is an inspection hold in the middle of the schedule.
A sewage ejector
Where gravity genuinely cannot be achieved, a pump can move waste uphill. It solves the geometry and introduces a mechanical device with a service life, a power requirement and a failure mode under a kitchen floor. It is a real option and it should be a last one.
Or: move the sink less far
Shortening the move can be the cheapest fix. At 8.8 feet or less this drain stays inside the existing floor and the work above is not needed. A sink two feet from where you wanted it, in a kitchen that came in on budget, is a trade worth weighing before demolition.
What to do with this answer
- Confirm the joist depth and direction yourself before you accept any plumbing price. A tape measure and a torch settle both.
- Ask the plumber to state, in writing, where the new line ties into the existing stack. The distance to that point is the number this whole page turns on, and it may not be the distance you assumed.
- If the margin above is under an inch, treat the route as unproven until somebody has opened it and looked.
- If this move is going ahead, it changes the trade count and the inspection count on the layout change page and adds days to the schedule.